8/13 Precon NOtes

Jud Permit check - Chris to Check with Austin

Coes - Permit issued

Charles is good, wanted to try and keep November 1

 

Potter - permit set updalkoad last

Jeremey confirmed town has permit sets

Jermey to ask for a soft expected dates

 

Dahlin - Jeff confirmed customer is ok to move the delivery date forward. 9/15 would be the earliest they can make the modular payment. 

Jeremey to Check to see if demo permit inspection is scheduled

 

Wolfram:

Chris to check plans, ask jeremey to submit to city

 

SChmidt

Jeremey dealin with sub permits. Town may require subs to come in and sign permits. 

 

Nery  - all set, waiting on KBS

 

Lavoie -  no action items

 

Hallowell - action items

 

Ouellette

- Jeremy to meet with SoPo tomorrow for per permitting meeting

- Jeff to conctact client to get jeremy access to basement

- Jeff to present updated plans to client today

- Jeff to get rest of colors by middle of this week

 

Adler - No action

Jeremy to log in check the plan they have match our plans and add the new ones. 

 

Meredith

- Design meeting tomorrow afternoon. Final detailed questions. 

- Probably don't like bathroom. 

- Megan or Chris to be on the call for real time changes

- Jeff started finishing choices, selecting virtually

-Tree work to be held as allowance due to lack of follow through

- Jeff to discuss financing and get that rolling

 

Lautenberger  - 

- Lauren answered questiosn about HVAC

- They are not ready with finances - we need more deail

- Lauren to per contract packet, chris to review

- Waiting on final quote fro factory to finish pricing

 

Mason

- Finishing section on Friday in office

- waiting on KBS/PBS quote back

 

Hornig - 

- Lauren to prepare contract packet

- Chris to block off time tomorrow 

- Test pits dug, water table is all set

- ZBA app submited week of 8.7

- Jeremy to update the site plan per the email - make ADU parrelle with hjosue

 

Hoemstart

- move to permitting updates next week

 

Santos

- Chris responding to email from them

- Lauren to schedule color selection 

- Chris to figure out what is next for Santos

 

Mullan

- No actions, waiting for Kevin to come back

 

Karpman 

- Design to get udpated design to Client by Friday

 

WAng - Initial design to client this week

 

Conlon - wait to kevin get back

Need to confirm:

- client ok moving the house back to a conforming 

 

OBrian - no action itesm

Surveyors been out there, 

Confirm bedroom conversion plan

 

Nguyen

- Chris to check on redlines 

- Laurenm to hold design accountable on delivery updated design work 

 

Karukin:

- Jeremy to initiate predesign work

- Jeff to confirm with Austin about reinspecting of existing house

 

Chris to set notification for new clients into predesign

*MA to Kevin

*Me to Jeremey

 

Cousineau

- Jeff waiting on initital design work

- Septic is done

- Jermey to update FS Input and sign off on items that are done. 

- Jeremy need to verify the dance studio doesn't cause issues. Try to label as a Home Occupation

 

Tobin

-  Meeting scheduled for Friday @ 3:00.