Pre Construction 8.21

 

COMPLETE:

BErgren

- 1 day of punch list, facia, oavers, miniplit head. Austin to schedule

 Newma

- panel rebalnce and sash replace - Kevin to coordinate next week


CONSTRUCTION

Delorme

- Site work to be completed today, she needed to reschedule her move

Meyer

- Tell meyer post will be follow up project

- Recommend 

Shore

- Chris to do final billing and' punch list

Freidman

- Water & sewer is ready to be hooked up

- Siding (waiting on window delivery to finish siding)

Davis:

- Need to order siding and deck material (Kevin To Order)

- Cedar decking from lowes

Powell

- Permits submitted, no action 

- Tim to contact Vermont Soap and book counter top work

Sankowski

- waiting on Electrical load calc to finalize permit

- tim to create traffic management plan

- Kevin to follow up with electrical on load calc (DUE THIS WEEK)

- Tim and Kevin to follow with Site work people  (DUE THIS WEEK)

BUTLER

- Tim to send Change order

WILSON

- Thursday meeting with the architect - Archetitect to comment on how the ADU blends with the existing house

- September 1st deadline to update plan set for ZBA materials 

RETALIC

- with client.  

Welsh

- waiting on PBs, contract this week. 


HUber

- Wiatin on janice for quote update

- contract in 2 weeks

Olsen-

Waiting on PBS

Gang

Waiting on PBS

-Spetic design is on Gang

Mulkerrins

- decided basement to be higher, FF of house to match existing house. 

- alissa updating plan