Ops Meeting Notes
Sep 5, 2023 | Operations Divide and Conquer
Attendees: Christopher Lee Austin Gregory Tim O'Reilly Alissa Marcano Santelli Jeff Bowman Kevin Whelan
Notes
- Chris using priority on deal card
- Delivery Scheduled
- Bomser
- Don’t have anything to do
- Hall
- Need a building permit
- Davis
- Schedule site work guys to come back based on latest lead time
- Need to order siding and decking
- Siding as primed
- Maybe another smooth option?
- Powell
- Foundation plan uploaded
- Moving forward with 36” sink and removing garbage cabinet
- Deposited and scheduled for Nov 7
- Sankowski
- Submitted electrical
- Need to nail down site work
- Kevin working with Miguel (mauri’s guy)
- Tim working with DJ Morris
- Hard date to know what’s going on is Friday
- Would need to delay delivery if not in place
- Tim taking point with building department
- Custom 10’ door
- Needs to be ordered
- Bomser
- Permitting
- Peter Smith
- Tim spoke with him once when they were talking about the permit and foundation plan
- Foundation guys and a late September/mid-October time frame
- Janice has everything they need for HERS modeling
- Need to make sure this gets through to sign off this week
- Butler
- Waiting on permitting
- Need septic information
- Wilson
- Waiting on zoning hearing
- Client wants to add a screened porch
- Can they add a porch within the 20’ setback of the reserve area?
- Peter Smith
- Contracting and Finishes
- Welsh
- Chris working on numbers
- Goldstone
- Ready to submit building permit
- Talked to them about option selection
- Mulkerrins
- On Tim to go over contract, currently has a blank contract
- Write up contract and have options table explicit of what we are doing and not doing
- Kevin - get quote from Matt Marby
- Garage removal/tree removal would be done
- Tim can meet Matt Tuesday the 12th
- Would need a finished site plan to go with the contract
- Tim
- Need to schedule color selection
- Then ready to go to finals
- Gleason
- Balls in Tim’s court to keep it moving through PBS
- Tim did color selection and it is low priority
- McGuire
- Quiet
- How many times have you reached out?
- Just once
- Per Chris, give them a call to check in
- Huber
- Heading to finals at PBS
- Jeff, double check plans
- Welsh
- Design Development
- Schneiderman
- Color selection Monday 9/11
- Waiting on PBS
- Submitted for confirmations
- Will be ready for a contract after colors
- Lining up someone for foundation
- Tim checking in with Janice
- Olsen Duplex
- Waiting on PBS
- Gang
- Meet and go over budget, see how they are feeling
- Have they communicated timeline?
- Spring move in
- Delivery would be late February
- Will exclude any well from contract
- Well recommended by Cushing & Sons needs some maintenance
- Yanok
- Alissa to follow up with PBS, it is overdue
- Shin
- Tim meeting with them on Thursday
- Hallowell
- Jeff to re-open line of communication
- Melander
- Mom is going to be interior designer, so there will be a “remote” dance
- Need to start moving through PBS
- Check what we need for permitting
- Expectations for delivery?
- She’ll check in with us in the next week
- They’ll know how much they will have from sale of house
- HMLP could apply
- If she wants a winter delivery, we need to know within the next two weeks
- She’ll check in with us in the next week
- Kevin - check with Adam Quinn when he is good excavating
- The well has been found - next to where the footprint of the house would be
- Graham
- Way over budget
- Enormous infrastructure to get utilities to lot
- Work with surrounding homeowners to try and keep project alive
- Way over budget
- HomeStart
- Hearing this Thursday
- Practical hardship variants
- Being presented by attorney for HomeStart
- Hearing this Thursday
- Schneiderman
- New projects
- Tim
- Pull more in after Mulkerrins, Gang, and Melander
- Tim has a lot more feasibility scheduled
- Jeff
- Pull in any
- Tim
- Feasibility study
- Start talking through financial questions people are having regarding the studies, try and get a higher close rate
- Handler
- Initial follow up
- Smith
- Initial follow up, client is gung ho
- Nichols
- DIY, seems positive
- Marissa Evans
- Looking good
- Johnson
- In Chris’ court
- Jeff/Austin meet with her in person
- Mullan
- Multi unit in P-town
- Due diligence with permitting/zoning
- Financing strategy/goals
- Sell one as condo
- One as affordable
- One as seasonal
- Wambolt
- Tim doing on way to Maine
- Lindberg
- Jeff to call with Alissa
- Higgins
- Chris to upload to folder
- Nelson
- In Chris’ court
Action items
- Davis - Tim to send email to client about cedar texture, can’t get smooth finish
- Sankowski - Tim to order the 10’ door
- Mulkerrins - Kevin to get quote for site work from Matt Marby
- Tim & Jeff - see what projects need status updates and Alissa will reach out