Pre Construction 8.21
COMPLETE:
BErgren
- 1 day of punch list, facia, oavers, miniplit head. Austin to schedule
Newma
- panel rebalnce and sash replace - Kevin to coordinate next week
CONSTRUCTION
Delorme
- Site work to be completed today, she needed to reschedule her move
Meyer
- Tell meyer post will be follow up project
- Recommend
Shore
- Chris to do final billing and' punch list
Freidman
- Water & sewer is ready to be hooked up
- Siding (waiting on window delivery to finish siding)
Davis:
- Need to order siding and deck material (Kevin To Order)
- Cedar decking from lowes
Powell
- Permits submitted, no action
- Tim to contact Vermont Soap and book counter top work
Sankowski
- waiting on Electrical load calc to finalize permit
- tim to create traffic management plan
- Kevin to follow up with electrical on load calc (DUE THIS WEEK)
- Tim and Kevin to follow with Site work people (DUE THIS WEEK)
BUTLER
- Tim to send Change order
-
WILSON
- Thursday meeting with the architect - Archetitect to comment on how the ADU blends with the existing house
- September 1st deadline to update plan set for ZBA materials
RETALIC
- with client.
Welsh
- waiting on PBs, contract this week.
HUber
- Wiatin on janice for quote update
- contract in 2 weeks
Olsen-
Waiting on PBS
Gang
Waiting on PBS
-Spetic design is on Gang
Mulkerrins
- decided basement to be higher, FF of house to match existing house.
- alissa updating plan