Pre Construction 8/28

Notes

  • Meyer
    • Work is happening this week
    • Need to pull trigger on HERS
      • Kevin to work with Chris to coordinate
    • May need to remove garage from scope, not competitive in pricing
      • Unless there is a finished ADU above it
  • Butler
    • Need HERS for permit sets
  • McGuire
    • Quiet
    • Maybe adjust plumbing numbers to entice
      • 5K off
  • Wilson
    • Meeting with architect was silly and we didn’t need to be there
  • Schneiderman
    • Waiting on PBS
    • Updates that Tim pushed through on a HubSpot ticket
    • Need plans with elevations Friday this week for a planning board hearing
  • Olsen Duplex
    • With Janice
  • Gang
    • On Tim’s plate
  • Melander
    • On Tim’s plate
  • Yanok
    • Waiting on PBS
  • Mulkerrins
    • pricing/contract this week
  • Shin
    • Went quiet
  • Gleason
    • Weird items that Tim needs to try and price
    • Picked 50-60% of finishes
  • Hollowell
    • Quiet, Chris tried to get in touch with them a week ago
  • Melander
    • Get her initial pricing
    • Kevin working on Electrical
  • Graham
    • Could go to contract
  • Gregory
    • Austin working with permitting on his camp
  • HomeStart
    • Winter demolition
    • Hearing that got scheduled for first week of September
  • Deposited Backlog
    • Chris owes plans to surveyor
    • Tim
      • Surveyor for Salem
      • Weston - garage as a location
        • Kevin investigate permitting in Weston
  • Feasibility
    • Jeannette Smith
      • Tim to finish and Chris to review
      • Waiting on conservation commission
    • McGibbon
      • Chris owes them today
    • Nelson
      • Uploaded pictures to update site plan
    • Alissa
      • Prep for Evans and Higgins
    • Tim NEW
      • 1 or 2 in professional advice that are probably ready
      • Prioritize western MA or Cape region